JEA’s William Burgess Water Main Work Is Set to Start Wednesday. It’s Expected to Run Into December 2027.

JEA, the Jacksonville-based utility, plans to begin laying a new 16-inch drinking-water main on Wednesday, November 18. The work covers parts of Robert E. Williams Road, Bill Howard Way and William Burgess Boulevard and is estimated to finish in December 2027. Temporary lane or road closures “may be needed.” No closure dates have been announced.

By Amelia Undertow · Published November 17, 2026 · County notice and project records checked November 17, 2026

Illustration of sections of large blue water pipe staged beside a freshly dug roadside trench, with an excavator and orange traffic barrels along a pine-lined boulevard at sunrise.
Illustration
Why it matters

If you drive William Burgess Boulevard or the two connecting roads, expect construction crews, utility flags in the right-of-way and, at times, lane or road closures for about a year. JEA says the pipe is meant to add water-system capacity for growth. It also says homes and businesses keep their access and that regular water, sewer and electric service will not be interrupted by the work.

What the notice says

Nassau County’s communications office posted JEA’s announcement at 6 a.m. on November 17. According to that notice:

Whose project it is

The notice says plainly that “this is a JEA project, not a project of the Board of County Commissioners.” Questions go to JEA Project Outreach at (904) 665-7500, not to the county. The county posted it as a courtesy, and it is not a county commission decision or county spending.

Where the pipe runs

The county notice does not draw the route. A project description from Degrove Surveyors, which says it did topographic and underground-utility survey work for the line in 2025 under contract to Jacobs Engineering for JEA, places it in Yulee. It describes the alignment as starting at an existing stub-out at JEA’s West Nassau Water Treatment Plant and running east and north along Robert E. Williams Road, Bill Howard Way and William Burgess Boulevard to the planned Crosstown Parkway extension.

That survey description gives the line as about 5,300 feet. JEA’s construction notice says about 4,400. The records reviewed do not explain the difference; a design-stage survey corridor and the final construction length are not always the same.

The Fix

Analysis and opinion. A 13-month job on a growing Yulee corridor deserves more than “closures may be needed.” Two simple steps would help drivers and the businesses along the route:

  1. Post the limits and the order of work. Say where on each road the pipe goes and which segment comes first, so people know when the crews will reach them.
  2. Give closure notice with dates. Publish each planned lane or road closure, with dates and detours, a few days ahead, and ask the county to carry it in the weekly road updates it already posts for its own projects.

What is still unknown

Primary sources

  1. Nassau County communications office, “JEA Announces Water Improvement Project,” November 17, 2026: pipe size, length and purpose; the three roads; anticipated start and estimated completion; work hours; closures, access and service statements; utility markings; JEA contact; statement that it is not a county project; checked November 17, 2026.
  2. Degrove Surveyors, “JEA William Burgess Boulevard 16-Inch Water Main,” project description: firm’s description of its 2025 survey work, the Yulee location, the alignment from the West Nassau Water Treatment Plant to the planned Crosstown Parkway extension, and an approximate 5,300-foot length; a contractor’s description, not a JEA or county record; checked November 17, 2026.

Status: Work is scheduled to begin November 18, 2026; this report does not confirm that it has started. JEA’s own project page could not be read for this report, and no closure schedule had been published in the records reviewed. The illustration does not show the actual work site. “The Fix” is this publication’s analysis and opinion.