Nassau Will Open Bids Wednesday to Tear Down and Rebuild a Home With State Housing Money
Nassau County will open contractor bids at 10 a.m. Wednesday, November 18, for a project that demolishes a home and builds a new one with State Housing Initiatives Partnership money. The county’s funding notice for 2025–26 caps that kind of award at $200,000 a home. The notice of the bid opening does not name the property, the bidders or a price.

This program can replace an unsafe house for a homeowner who cannot afford to fix it. It runs on state housing money the county hands out each year, with income limits, a short application window and rules about who can apply. The county’s own documents disagree on one of those rules: whether a mobile home qualifies.
What happens Wednesday
The county posted a notice on November 13 for solicitation NC26-016-RFP, which it titles the “SHIP Demolition and Reconstruction Project,” No. 242EC-514. Bids will be opened at 10 a.m. Wednesday, November 18, at the Robert M. Foster Justice Center, second floor, Suite 456, 76347 Veterans Way, Yulee.
The notice says the county’s procurement director will open the bids and that no decisions will be made at the meeting. The public may attend and speak. It cites two state laws, sections 255.0518 and 286.011 of the Florida Statutes, which cover the public opening of construction bids and open meetings.
The notice does not give the address of the home, the number of bidders, an estimated cost or a date for awarding a contract. We did not review the solicitation package itself for this report. No contract has been awarded.
What the program pays for
SHIP is a state program that sends housing money to counties and cities. Nassau County’s SHIP page says the Florida Housing Finance Corporation administers it and that the county has selected the firm Accenture to help carry it out locally.
The county’s funding notice for state fiscal year 2025–26 announced $731,755 in available money across six kinds of help. For demolition and reconstruction it says: “The maximum amount of funds that may be awarded per unit is $200,000.” The notice describes that option as replacing a home that is more than 51% structurally unsound with a new site-built home.
The same notice lists a lower cap, $125,000 a home, for owner-occupied rehabilitation, which pays for repairs to correct code violations. The county’s Local Housing Assistance Plan for 2024–2027 says reconstruction may be used when rehabilitation is not enough, for homes found “more than fifty-one (51%) structurally unsound” by a certified housing rehabilitation inspector or building inspector.
That plan also explains why a bid opening is happening at all. It says the work “will be performed by contractors awarded through a formal competitive Request for Proposal.” The county, not the homeowner, runs the bidding.
The records do not say which fiscal year’s money pays for project 242EC-514.
Who qualifies
From the 2025–26 funding notice, the county’s SHIP page and its rehabilitation page:
- Owner and occupant. “The homeowner must claim homestead exemption and the home must be occupied to qualify,” the funding notice says.
- In Nassau County, and the household’s primary residence.
- Within the income limits. The rehabilitation page limits repair awards to very-low- and low-income homeowners and says moderate-income households are not eligible for that award.
- No SHIP help in the past 10 years. For reconstruction, the notice says applicants “are limited to assistance once.”
- Not a rental or a condominium.
The county’s 2026 income limits page lists the low-income ceiling at $60,900 for a one-person household and $86,950 for a household of four. The very-low-income ceilings are $38,050 and $54,350.
Applications are evaluated in the order received, with priority for people with special needs as state law defines them, according to the funding notice.
What the homeowner owes
The help is a loan secured by a mortgage on the house, with no interest and no monthly payment while the owner stays in good standing. For rehabilitation, the county’s strategy document sets a 10-year term and says “10% of the principal is forgiven annually.”
The 2024–2027 plan lists what puts a reconstruction loan in default during its term: selling or transferring the home, turning it into a rental, losing the homestead exemption, or no longer living there as a primary residence. The plan also says a homeowner “will not be considered for future SHIP assistance after the new home is constructed.”
What earlier rebuilds looked like
The county has described two finished rebuilds in its own newsletter. Keys to a 1,001-square-foot, three-bedroom house were handed over on September 5, 2025, after a 79-day build that replaced a 1989 home with no central heat or air, the county reported. On October 13, 2025, a second homeowner received a two-bedroom house that replaced a block home more than 70 years old with a deteriorating foundation and a failing septic system; that build took 98 days.
Both posts name Eason Development as the builder. Neither gives a cost.
On August 26, 2026, the county received a 2026 SHIP award at the Florida Housing Coalition’s statewide conference in Orlando, in a category covering rehabilitation, purchase assistance and new construction, according to a county post dated September 3.
Where the county’s documents disagree
- Mobile homes. The 2025–26 funding notice says of reconstruction: “Mobile homes, rental units, and condominiums are not eligible for assistance under this strategy.” The SHIP page also says mobile homes are not eligible. The 2024–2027 plan, as amended by the commission on March 9, 2026, says in its reconstruction section: “Mobile homes are eligible for demolition and replacement.”
- Which notices are posted. The county’s Notices of Funding page listed notices for 2022–23, 2023–24 and 2024–25 when checked. The 2025–26 notice is in the county’s document library but was not listed there.
- A label. The income limits page heads its moderate-income column “20%.” The dollar figures in that column are well above the low-income column.
The Fix
Analysis and opinion. A homeowner in a failing mobile home who reads the county’s SHIP page will conclude there is no point in applying. One who reads the adopted plan will conclude the opposite. The plan is the document the commission voted on. Three steps would clear this up:
- Say in one place whether a mobile home can be replaced, and make the web page, the funding notice and the plan match.
- Post the current funding notice on the Notices of Funding page, with the next application dates when they are set.
- Publish the result of Wednesday’s opening: who bid, how much, and when a contract goes to a vote.
If you think your home might qualify
The SHIP page has an application form labeled 2026 and lists Llewellyn Esteban of Accenture as the contact, at (850) 681-3717. The income limits page gives a second Accenture number, 850-328-2255. The page lists no open application period. The last one in the county’s notice ran from July 15 to August 15, 2025, and that notice says everyone interested must apply or re-apply.
To attend Wednesday’s opening with an accommodation, the notice says to contact the County Manager’s Office at 904-530-6010 at least 72 hours ahead.
What remains unanswered
- How many contractors bid, and at what prices.
- When a contract will be awarded. County notices have canceled the commission’s regular meetings on November 18 and November 23, as we reported November 13.
- How much SHIP money Nassau has for 2026–27 and when the next application window opens.
- Whether a mobile home can be replaced under the program.
Primary sources
- Nassau County, Notice of Solicitation Opening NC26-016-RFP, posted November 13, 2026: project name and number, date, time, place, who opens bids, statutes cited, accommodation contact; checked November 15, 2026.
- Nassau County, Notice of Funding Availability, SHIP, state fiscal year 2025–2026: $731,755 total, per-unit caps, eligibility rules, application dates of July 15 to August 15, 2025, order of evaluation; checked November 15, 2026.
- Nassau County Local Housing Assistance Plan, fiscal years 2024–2025 through 2026–2027, with Resolution 2026-022 adopted March 9, 2026: reconstruction strategy, contractor selection, default conditions, mobile home sentence; checked November 15, 2026.
- Nassau County, SHIP – Affordable Housing Program page: administrator, eligibility list, application form, contact; checked November 15, 2026.
- Nassau County, Rehabilitation page and Owner Occupied Rehabilitation strategy document (template effective July 1, 2024): income categories, $125,000 cap, loan term and forgiveness; checked November 15, 2026.
- Nassau County, 2026 Income Limits page: income ceilings by household size; checked November 15, 2026.
- Nassau County, Notices of Funding page: notices listed; checked November 15, 2026.
- The County Insider, Nassau County’s newsletter: September 11, 2025 and October 21, 2025 posts on completed rebuilds, and September 3, 2026 post on the SHIP award; checked November 15, 2026.
Status: Wednesday’s meeting is a bid opening. No contractor has been selected and no contract has been awarded. The $200,000 figure is the program’s per-home cap in the county’s 2025–26 funding notice, not a bid or a price for this project. The solicitation package was not reviewed for this report. The illustration does not show the home in the project. “The Fix” is this publication’s analysis and opinion.